When to Use a Risk Matrix and Risk Tolerable Criteria

2

We don’t recommend using a risk matrix during PHAs/HAZOPs. matrices are good tools to teach risk concepts, but in a well led PHA/HAZOP they reduce quality more than they increase quality. To see much more details, download and read this free paper: http://www.process-improvement-institute.com/_downloads/Optimizing_PHA-HAZOP_While_Maximizing_Brainstorming.pdf We use a risk matrix and a risk tolerance criteria only when doing a LOPA (to address …

Read More

When should PHAs (HAZOPs, etc.) Be Performed During Major Projects?

0

The short answer is you need to perform PHAs in phases, from conceptual stage, through preliminary and detailed design, and then complete these during the pre-commissioning stages (as mentioned by Bryan). The PHAs build upon each other and the completion of the final phase PHA becomes the Baseline PHA. The tools used change from phase-to-phase, with What-if and some high …